May 15, 2012 — Contractors from 12 telecom construction companies received details last night (May 14) to bid on a broadband Internet expansion project for Bois Blanc Island, Mich. TDS Telecommunications Corp. (TDS®) hosted the pre-bid meeting in Cheboygan to outline the project. Bids are due to TDS by June 4, 2012.
Once complete, nearly 300 customers in TDS’ Island Telephone Company (outlined last night) in Michigan will have access to a high-speed Internet connection. {Click on company name above for map detailing where high-speed Internet services will be expanded.}
TDS has received funding, in part, for 44 projects from the American Reinvestment and Recovery Act via the United States Department of Agriculture’s (USDA) Rural Utilities Service (RUS). In total, TDS is receiving funding from the RUS that will lead to 27,000 more households gaining access to broadband Internet services by the end of 2013.
Today, TDS offers Internet service to more than 93 percent of their customers nationwide. The remaining seven percent live in mostly rural areas where distance and topography issues push the limits of technology. According to TDS, these issues make it very difficult to develop a solid business case to expand broadband services. The ARRA funds make it possible for companies, like TDS, to expand their networks and deliver services to people currently without access to a reliable high-speed Internet connection.
“The pre-bid meeting is a critical piece to getting this network built,” says Larry Boehm, director of Network Implementation and Optimization for TDS. “We outlined the project and the timelines. Now, contractors have a chance to submit their bid and demonstrate they can meet the project expectations on deadline. We’re looking to hire the firms quickly so construction can get underway this spring. Our customers are ready and waiting for access to high-speed Internet service.”
Background: In February 2009, Congress passed the American Recovery and Reinvestment Act of 2009; it was signed by President Obama shortly after passage. In August 2009, TDS submitted 13 applications for broadband funding. In December 2009 and January 2010, TDS was awarded two grants totaling $12.5 million from the RUS (one of the two federal agencies administering the federal broadband stimulus program) to expand broadband access in Chatham, Mich. and Butler, Ala.
In March 2010, TDS submitted 46 applications for round two funding consideration. In August, TDS was awarded 42 grants (including the four Ind. projects and the Mich. project) bringing the company’s total awards to 44 and nearly $136 million to expand high-speed Internet services in 20 states. Engineering firms were selected and announced in February 2011, and now pre-bid meetings are taking place. Construction on many sites will begin this spring. Most networks will be completed in 2012 and the remaining in 2013.